Single point load cell installation: mounting, wiring and symptoms.

Identify a chart and record your installation for support.

Go to the inputs and results ↓

WIRING + OBSERVATIONS

Select a source chart.

Installation review inputs

Before mechanical inspection or resistance testing, unload and isolate the equipment using the approved site procedure. Qualified personnel should use the actual sensor and instrument manuals. Never change wiring while energized.

Unknown model: no wire colours or jumpers are assigned. Send the full code, nameplate, source cable chart and indicator terminal document.

Select an observed behavior to see the evidence checklist. This tool does not classify a sensor as damaged.

Carry these observations into the support RFQ

FUNCTION BEFORE COLOUR

Excitation, signal and sense have different jobs.

  1. 1Sensor bridge: excitation powers the measuring bridge
  2. 2Signal pair: small differential output goes to the instrument input
  3. 3Sense pair, when fitted: supports the documented excitation-feedback arrangement
  4. 4Shield/body/earth: follow the local EMC and instrument design
ConfigurationFunctions normally exposedReview before connection
Analog four-wireEXC+, EXC−, SIG+, SIG−; shield separatelyCable calibration, exact functions, instrument input type and any required manual-specific links
Analog six-wireFour bridge functions plus SEN+ and SEN−; shield separatelyWhether the instrument supports sense, actual terminations and the manufacturer-approved connection arrangement
Connector/digital/unknownNo analog pinout inferred from conductor countActual protocol, supply and connector pin assignment; leave the chart unassigned until identified

Blue can mean three different functions.

These are identified source examples. They demonstrate why a generic manufacturer-name colour lookup cannot establish an installed connection.

Specific referenceBlue conductor in this sourceSource scope
SPL-SSW-101EXC+Own reference chart, SPL-REF-20261122.1
SPL-HVY-101SEN−Own reference chart, SPL-REF-20261122.1
Original Flintec PC6 six-conductor optionSEN+A28-Rev11-GB, PDF page3; verify the supplied option

Do not merge these charts into a colour-to-colour replacement instruction. Compare the original and proposed function labels, polarity, cable/connector option, excitation and instrument requirements independently.

Review original-model electrical and mechanical interfaces
stainless single point ip67 dual aperture long beam with top sealing patch and side cable entry — supplier-source product reference
SPL-SSW-101 reference geometry. The visible cable exit and sealing area are installation review points; the photograph does not verify the actual supplied wiring or assembly IP scope.

Mount on defined pads and leave the flexure free.

Confirm the fixed/loading ends, clean mounting faces, spacer contact and permitted fastener engagement. Keep the active beam, cable, platen and stops clear through the approved working travel. Contact or debris can create an unintended load path.

Review plate flatness and rigidity against the actual source drawing. This guide does not assign a universal flatness value or fastener grade. Preserve the drawing revision and assembly inspection record.

Review spacer and overload-base principles

M6 does not identify one universal torque.

Original source exampleConditions stated by that sourceBoundary for an SPL installation
HBK PW15AH,10–100 kgM6; minimum property class10.9;14 N·m reference, with screw-manufacturer dimensions consideredA02435 03 Y00 02, English section4.2 / PDF page10; original model only
Flintec PC6M6 class8.8;10 N·m; source explicitly assumes oiled threadsA28-Rev11-GB, PDF page3; original source conditions only
Current SPL referencesThread/depth data available; approved joint torque not suppliedRequest the exact bolt, lubrication, engagement, plate and tightening procedure; neither original example is assigned to SPL

Keep cable changes inside the calibration and instrument review.

Shortening

The cited HBK PW/SP manual distinguishes its four-wire cable calibration from six-wire configurations. Confirm your own supplied model's instructions and recalibration requirements before cutting a cable.

Extension and connector

Record cable type/length, splice position, shield continuity, conductor functions and environmental protection. Sense support and connection location depend on the instrument and sensor arrangement.

EMC and routing

Review routing near drives/power wiring and the local shield/earth scheme. A shield is not a substitute for an engineered protective-earth or potential-equalization path.

HBK PW/SP A02323, English section5 provides the identified original configuration examples; follow the actual supplied manuals for implementation.

Bridge resistance and sense functions need the exact design.

SPL referenceInput / output resistanceCable referenceSource chart
SPL-CMP-101405 ±5 Ω / 350 ±3 Ω4 mm diameter × 350 mm; 4 wires plus shieldOpen reference PDF
SPL-CMP-102380 ±40 Ω / 380 ±40 Ω4 mm diameter × 400 mm; 4 wires plus shieldOpen reference PDF
SPL-SSW-101420 ±20 Ω / 350 ±10 Ω5.2 mm diameter × 1,600 mm; 6 wires plus shieldOpen reference PDF
SPL-ALU-101420 ±20 Ω / 350 ±10 Ω5.3 mm diameter × 2,000 mm; 6 wires plus shieldOpen reference PDF
SPL-HVY-101380 ±20 Ω / 350 ±10 Ω6.3 mm diameter × 2,500 mm; 6 wires plus shieldOpen reference PDF
SPL-SSW-102380 ±20 Ω / 350 ±10 Ω6 mm diameter × 3,000 mm; 6 wires plus shieldOpen reference PDF
SPL-SSW-103390 ±5 Ω / 350 ±5 Ω6 mm diameter × 1500 mm; 6 conductors plus shieldOpen reference PDF

Qualified personnel should isolate the transducer from the instrument and other electrical paths according to both manuals before resistance testing. Compare the correct EXC or SIG pair and the actual model specification. An in-circuit reading or one unexpected value does not independently establish a failed sensor.

Insulation testing is a separate procedure. No voltage, threshold or connection arrangement is preselected here; obtain the approved model/electronics procedure before testing.

Record symptoms as evidence, not a damage verdict.

Observed behaviorPossible causesEvidence to retain
Position-dependent / corner errorUnintended contact, frame distortion, mounting interface, eccentric load outside the approved envelope or calibration conditions.Record centre and corner readings using the approved load/placement plan, plus pre/post zero. Photograph spacers, stops and cable clearance. Do not file the sensing beam.
Zero drift / unstable readingTemperature change, settling product, air movement, cable strain, unintended contact, moisture or electrical interference.Record time, ambient/process temperature, load state and whether nearby equipment was operating. Inspect clearances and visible cable damage with the equipment isolated.
No reading / instrument input errorInstrument setup, cable/connector interruption, mismatched functions, excitation compatibility or an actual bridge fault.Capture the instrument model, error code, approved terminal chart, full sensor code and whether the cable is four- or six-wire. Do not identify terminals by colour alone.
Reading direction is reversedApplied load direction, instrument polarity/configuration or an incorrect signal-function connection.Record the applied direction and known-load response, sensor orientation and the actual terminal-function chart.
Change after cleaning / moisture exposureCable entry/connector exposure, retained liquid, chemical/temperature effects, contamination contact or sensor damage.Record cleaning temperature, pressure, chemistry, timing and installation drainage; photograph the entry and connector without opening sealed sensor parts.
Change after impact / overloadShifted stops/mounting, cable damage, mechanical obstruction or permanent sensor/frame damage.Unload and isolate the equipment. Record the event, previous calibration/zero and visible assembly condition. Preserve the full model code and installation photos.

The Flintec LCT-11 guide distinguishes cable, bridge, moisture and other possible causes in its own instrument workflow. Its tester limits and multi-cell examples do not establish acceptance limits for an isolated single-point installation.

Use a controlled centre/corner record with pre/post zero.

Agree the model-specific permitted mass, positions, settling conditions and error limits before testing. The following is a recording framework, not a universal statutory test or permission to load beyond the rated envelope.

Record position / stateRecord with each readingDecision boundary
Unloaded referenceStable zero, time, temperature, instrument/filter settingsIdentify warm-up, settling and assembly conditions
Centre + four agreed off-centre positionsApplied mass, placement coordinates, settled reading and repeatsUse the actual model/assembly's permitted loading and agreed acceptance criteria
Unload after the sequenceReturn-to-zero, elapsed time and visible contact/cable changesInvestigate differences with source-specific controlled checks
  1. 1Freeze the installation drawing, model code and test procedure.
  2. 2Isolate for mounting/cable inspection; restore only under the approved procedure.
  3. 3Record the permitted load sequence and operating conditions.
  4. 4Separate observations, possible causes and confirmed test findings.
  5. 5Review corrective action, repeat the agreed checks and retain the final revision.

Send three views and the function chart for a useful support review.

Nameplate and source revision

Keep the full order code, capacity, cable option and approval markings readable. Type the code in the inquiry so every suffix survives the handoff.

Mounting and free travel

Show fixed/load pads, spacers, stops, supports and cable exit. Add the dimensioned assembly drawing; a photo cannot establish hole pitch, gap or thread depth.

Instrument terminals

Capture the instrument model, terminal-function labels and approved wiring chart. Include error/event history and previous calibration records where available.

Attach approved files in your email application. Ask about an NDA before sending confidential drawings. A damaged-cell replacement should follow identified source/code and interface review, rather than a promised universal swap or delivery time.

Open the original-model review centre

SOURCE REVIEW / 22 NOVEMBER 2026

Original documents define their own models and conditions.

The SPL reference PDFs use the reviewed source catalogue revision. Independent manufacturer documents below support the identified original examples and installation distinctions; they do not assign their ratings, torque, pinout or approvals to an SPL configuration.

Installation and wiring decisions

Can I connect a load cell from wire colours alone?

No. Confirm the exact supplied model, cable/connector option and instrument terminal-function chart. The same colour can mean excitation or a sense function in different references; a brand name or cable count alone is not a connection instruction.

How do four-wire and six-wire load cells differ?

A typical analog four-wire bridge exposes excitation plus/minus and signal plus/minus; a six-wire configuration adds sense functions for the instrument. The shield is separate from those counts. Actual terminations, sense support and any bridging must follow both supplied manuals.

Is there one jumper rule for all four-wire and six-wire conversions?

No. Identify the sensor functions and instrument architecture first. Some documented original configurations specify same-polarity sense/excitation connections or amplifier-side links, but their location and conditions are manual-specific. The chart tool does not prescribe a universal jumper.

May I shorten or extend the cable?

Check the actual model and calibration conditions. The cited HBK PW/SP instructions distinguish four-wire cable calibration from six-wire sense configurations. Extension type, termination, shielding, excitation and recalibration requirements still need review; never infer that every six-wire cable modification is unrestricted.

Does an M6 thread establish the tightening torque?

No. The original PW15AH and PC6 examples have different fastener/torque conditions despite M6 callouts. Use the exact supplied sensor and joint specification, including bolt grade, lubrication, usable engagement and plate material. No universal SPL torque is assigned here.

What should I record for a centre/corner check?

Use the approved test mass and placement plan within the actual model/assembly limits. Record the source drawing, capacity, platen dimensions, centre and four position readings, pre/post zero, instrument settings, environment and agreed error criteria. This is a record framework, not a universal legal-metrology test method.

Do unstable readings prove moisture ingress or sensor yield?

No. Mechanical contact, product movement, temperature, cable strain, interference, instrument configuration and damage can produce overlapping symptoms. Record the event and conditions, then follow the model-specific isolation and testing procedure before deciding.

Should every cell measure 350 ohms?

No. Input and output resistances are separate specifications and depend on the design. Use the selected reference PDF and actual order revision; instrument connections and parallel paths can alter a measurement. An out-of-range observation needs a controlled isolated test and source comparison.

Can I use a universal insulation-test voltage?

No. Agree the manufacturer-approved procedure, voltage, connections and instrument isolation before any insulation test. Do not apply a generic high-voltage test through connected electronics or infer an SPL test condition from another manufacturer sheet.

What if my sensor is an original brand or an unknown variant?

Leave the SPL chart unselected and enter the complete installed code. Send the nameplate, mounting and indicator-terminal photos with the source diagram. The support request retains your observations without assigning a wire chart or confirmed replacement.

DRAWING + INPUTS + ACCEPTANCE SCOPE

Send the installed code, function chart and observations.

Use the tool's review action to retain your entered values in the editable engineering brief. Attach the approved drawing, nameplate or test records in your own email application.

Return to my worksheet / observations

Start a blank installation inquiry

The calculations and symptom lists organize a review. Agree the actual supplied model, assembly, source revisions and tests before release.